Spring Lake Coverage Map – 2020

HAB has downloaded and processed the alum application data from the barge’s guidance and dose control computer system.  The 2020 Spring Lake coverage map shows each individual application path that was recorded over the course of the Spring Lake application.  We are extremely pleased with the precise application and uniform coverage of the application zones. …

2020 Application Completed!

Thursday (5/14) the 2020 Spring Lake alum application project was completed!  We had a few wind delays, but as planned the exact dose of 249,000 gallons of alum was applied in a precise, uniform, and most importantly, safe manner.  There is no greater measure of success than safety and Spring Lake project adds to our…

Mobilization and First 3 Days of Application

HAB spent Sunday afternoon and Monday morning of this week preparing equipment for the 2020 Spring Lake alum application project. This included assembly of the barge’s application boom, launching the barge into the lake, setting up on-shore storage tanks and confirming the delivery plan for the alum. The staging area was restricted to keep lake…